Latest quarter
Ormat reported third-quarter revenue of $275.1 million, above the consensus of $246.1 million, and adjusted earnings of $0.56 per share, above the consensus of $0.36. Revenue rose from $249.7 million a year earlier, while diluted earnings per share increased to $0.51 from $0.39.
The company’s filing shows energy storage revenue rose to $49.9 million from $20.4 million, helped by high availability and higher energy rates at PJM facilities as well as contributions from new facilities. Electricity revenue fell to $163.7 million from $167.1 million, primarily because a hurricane-related outage reduced generation at Puna. Product revenue slipped to $61.5 million from $62.2 million, which the filing attributed mainly to project progress and revenue recognition timing.
Ormat’s gross margin increased to 28.1% from 25.6%. Free cash flow was $20.2 million, compared with −$102.1 million a year earlier.
| Q3 FY2026 | Q3 FY2025 | Change | |
|---|---|---|---|
| Revenue | $275.1 million | $249.7 million | 10.2% |
| Diluted EPS | $0.51 | $0.39 | 30.8% |
| Gross margin | 28.1% | 25.6% | 2.5 percentage points |
| Operating margin | 16.4% | 16.2% | 0.3 percentage points |
| Free cash flow | $20.2 million | −$102.1 million | — |
| Against the consensus | Reported | Consensus | Result |
|---|---|---|---|
| Adjusted EPS | $0.56 | $0.36 | Beat by 55.6% |
| Revenue | $275.1 million | $246.1 million | Beat by 11.8% |
Adjusted EPS is the figure the consensus estimates, not the GAAP EPS above.
Guidance
Ormat now expects 2026 energy storage gross margin of 50.0%–55.0%, up from its previous 40.0%–50.0% range. It expects $13.0 million of adjusted EBITDA to be attributable to minority interests, compared with its previous expectation of $17.0 million.
| Metric | For | Guide | Previous guide | Change |
|---|---|---|---|---|
| EBITDA, Non Gaap Annualized Run Rate Excluding Egs | FY2030 | $1.0 billion | — | New |
| Revenue, Annualized Run Rate Excluding Egs | FY2030 | $1.5 billion | — | New |
| Gross margin, Electricity | FY2030 | 40.0% | — | New |
| Units, Energy Storage Capacity Gw | FY2030 | 1.5–1.6 | — | — |
| Units, Electricity Capacity Gw | FY2030 | 2–2.1 | — | — |
| Units, Operating Capacity | FY2030 | Ormat expects to approximately double its year-end 2025 capacity by the end of FY2030. | — | — |
| Units, Operating Portfolio Gw | FY2028 | 2.6–2.8 | — | — |
| Capex, Product and Business Development | Q4 FY2026 | $22.0 million | — | New |
| Capex, Egs | Q4 FY2026 | $80.0 million | — | New |
| Capex, Energy Storage | Q4 FY2026 | $90.0 million | — | New |
| Capex, Electricity | Q4 FY2026 | $157.0 million | — | New |
| Capex | Q4 FY2026 | $287.0 million | — | New |
| Tax rate | Q4 FY2026 | −15.0% | — | New |
| Gross margin, Energy Storage | FY2026 | 50.0%–55.0% | 40.0%–50.0% | Raised |
| Gross margin, Product | FY2026 | 18.0% | 18.0% | Held |
| Gross margin, Electricity | FY2027 | Ormat expects electricity gross margin to jump in FY2027. | — | — |
| Gross margin, Electricity | Q4 FY2026 | Ormat expects Q4 FY2026 electricity gross margin to be slightly above the prior-year level. | — | — |
| EBITDA, Non Gaap Minority Interest | FY2026 | $13.0 million | $17.0 million | Cut |
| EBITDA, non-GAAP | FY2026 | $640.0 million–$650.0 million | — | New |
| Revenue, Energy Storage | FY2026 | $160.0 million–$170.0 million | — | New |
| Revenue, Product | FY2026 | $310.0 million–$320.0 million | — | New |
| Revenue, Electricity | FY2026 | $700.0 million–$710.0 million | — | New |
| Revenue | FY2026 | $1.2 billion–$1.2 billion | — | New |
| Gross margin, Electricity | FY2026 | Ormat expects electricity gross margin to improve toward the end of FY2026. | — | — |
| Units, Operating Portfolio Gigawatts | FY2028 | 2.6–2.8 | — | — |
| Capex, Egs | FY2026 | $20.0 million | $20.0 million | Held |
| Capex, Energy Storage | FY2026 | $129.0 million | $111.0 million | Raised |
| Capex, Electricity | FY2026 | $281.0 million | $436.0 million | Cut |
| Capex | FY2026 | $449.0 million | $587.0 million | Cut |
| Tax rate | FY2026 | 15.0% | −20.0%–−15.0% | Raised |
| Units, Egs Pilot Capacity Megawatts Each | FY2027 | 2–4 | — | — |
| Units, Generating Capacity Additions Megawatts | FY2028 | 216 | — | — |
| Units, Portfolio Capacity Gigawatts | FY2028 | 2.6–2.8 | — | — |
| Gross margin, Electricity Margin Increase | FY2027 | 1.00%–2.00% | — | New |
| Gross margin, Electricity Margin Increase | FY2026 | 1.00%–2.00% | — | New |
| Dividend, Per Share | Q4 FY2026 | $0.12 | Q3 FY2026: $0.12 | Held |