Kodiak Gas Services, Inc.

KGS

Energy Oil & Gas Equipment & Services

Kodiak Gas Services, Inc.’s revenue for fiscal 2025 (year ended December 2025) was $1.3 billion, up 12.8% from fiscal 2024.

Revenue
+24.5%
EPS
n/m
Free cash flow
n/m
Total debt
+7.30%

Quarter to September 2026, against a year earlier

41.38 1.09 +2.71% Wed 4:00pm ET

After hours trading: 41.37, down 0.02%, last trade Wed 7:53pm Eastern.

Market cap
$4.2B
P/E
24.0×
Fwd P/E FY26e
19.1×
Dividend yield
4.78%
F-score
6/9
ROIC
5.80%
Net debt / EBITDA
4.0×
Payout ratio
1.2×

Kodiak Gas Services, Inc. (KGS) Earnings & Analysis

Updated · Covers results through Q3 FY2026 · Earnings call · Latest filing 10-Q filed Nov 9, 2026 · How this is made

Latest quarter

Kodiak reported Q3 FY2026 revenue of $401.8 million, up from $322.7 million a year earlier and above the consensus of $387.2 million. Adjusted earnings per share of $0.70 also beat the consensus of $0.64; diluted earnings per share were $0.70, compared with −$0.17 a year earlier.

CFO John Griggs attributed most revenue growth to the addition of power infrastructure, while the filing said compression revenue benefited from price increases and more revenue-generating horsepower. The filing attributed growth in other services primarily to station construction and customer-requested services and materials, partly offset by lower field service demand.

Kodiak’s gross margin was 64.5%, compared with 64.0% a year earlier, while operating margin rose to 34.5% from 19.9%. The filing said the prior-year quarter included a loss on the sale of its Mexico operations and an accrual for interest and penalties related to a Texas settlement offer. Free cash flow was −$26.6 million, compared with $20.3 million a year earlier.

Q3 FY2026 Q3 FY2025 Change
Revenue $401.8 million $322.7 million 24.5%
Diluted EPS $0.70 −$0.17 —
Gross margin 64.5% 64.0% 0.5 percentage points
Operating margin 34.5% 19.9% 14.6 percentage points
Free cash flow −$26.6 million $20.3 million —
Against the consensus Reported Consensus Result
Adjusted EPS $0.70 $0.64 Beat by 9.38%
Revenue $401.8 million $387.2 million Beat by 3.78%

Adjusted EPS is the figure the consensus estimates, not the GAAP EPS above.

What management said on the call

CFO John Griggs said power infrastructure drove most of Kodiak’s revenue growth, with data center commissioning work and extensions of short-term contracts contributing to a sequential increase in power revenue. Executive Robert McKee said customers were keeping power equipment longer as they waited for grid connections, and Kodiak was weighing renewals against moving equipment to long-term contracts.

Griggs said compression infrastructure’s adjusted gross margin was 70.0% in Q3 FY2026, unchanged from the prior quarter despite higher lube oil costs. He said a supplier arrangement had eliminated nearly all month-to-month lube oil price volatility going forward. Power infrastructure’s adjusted gross margin was 75.0%; Griggs attributed its sequential revenue increase to commissioning work and contract extensions.

Asked about compression pricing, Griggs attributed the sequential decline in revenue per ending horsepower to operating lease buyouts and the termination of a high-revenue, low-margin contract. McKee said pricing on contracts put in place during the quarter increased sequentially, but Kodiak does not report those prices publicly. He also said much of the horsepower installed during the quarter contributed only a partial quarter of revenue and would contribute for the full quarter in Q4.

On power investment, McKee said site preparation had begun at the West Texas data center, with deployment starting around year-end and a goal of energizing the project before the end of Q1 FY2027. Griggs said Kodiak had committed to buy equipment from Baker Hughes through 2031, involving more than approximately $1.4 billion in capital, but could withdraw if necessary. McKee said demand for both compression and power was putting pressure on upstream supply chains.

Asked about the other services business, Griggs said Kodiak had brought in new leadership for aftermarket services after underinvesting in it. He expects power projects to increase station construction and project management work, though he said that work would be uneven as power plants are built.

Guidance

Kodiak raised its FY2026 adjusted EBITDA guidance to $840.0 million–$860.0 million. Griggs said the company raised the low end of its full-year compression infrastructure adjusted gross margin range to 69.5%–70.5%, from its prior range of 69.0%–70.5%. He also reduced the FY2026 power infrastructure growth capital expenditure forecast to $350.0 million–$400.0 million, citing some unit deliveries moving into 2027 and a firmer payment schedule for supporting plant equipment.

Metric For Guide Previous guide Change
EBITDA, non-GAAP FY2026 $840.0 million–$860.0 million — New
Gross margin, Power Infrastructure, non Gaap Q1 FY2027 Kodiak expects power infrastructure gross margin to recover somewhat in the first quarter. Q4 FY2026: Kodiak expects power infrastructure gross margin to dip in the fourth quarter. —
Gross margin, Power Infrastructure, non Gaap Q4 FY2026 Kodiak expects power infrastructure gross margin to dip in the fourth quarter. — —
Units, Power Infrastructure, west Texas Data Center Q1 FY2027 40 — —
Units, Power Infrastructure, megawatts FY2026 29 — —
Units, Power Infrastructure, megawatts Q4 FY2026 16 — —
Units, Compression Infrastructure, horsepower FY2026 170000 — —
Capex, Power Infrastructure, growth FY2026 $350.0 million–$400.0 million — New
Gross margin, Compression Infrastructure, non Gaap FY2026 69.5%–70.5% — New
Capex, Power Infrastructure FY2026 $400.0 million–$450.0 million — New
Capex, Compression Infrastructure FY2026 $280.0 million–$300.0 million — New
Free cash flow, Discretionary Cash Flow, non Gaap FY2026 $570.0 million–$600.0 million — New
Units, Power Infrastructure Fleet FY2030 2 — —
Units, Power Infrastructure Deliveries FY2030 400 — —
Units, Power Infrastructure Deliveries FY2029 400 — —
Units, Power Infrastructure Deliveries FY2028 400 — —
Units, Power Infrastructure Deliveries FY2027 400 — —
Units, Power Infrastructure Deliveries FY2026 50 — —
Units, Compression Infrastructure Fleet FY2030 5200000 — —
Units, Compression Infrastructure Fleet Additions FY2026 170000 — —